2016 Bond Budget

$2,210,000

School-determined Budget

$50,000

School Type

Elementary School

Original Construction Date

1923

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Project Updates

 Quality Learning Environments

Status: Complete
Scope of Work:
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria).

 Maintenance

Status: Complete
Scope of Work: 
  • Interior LED lighting upgrade
  • Replace selected roofing
  • Improve existing cooling and ventilation systems

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

Photos