School-determined Budget

$140,000

Original Construction Date

1926

Facility Type

Shared Campus: STRIVE Prep - Lake and Lake International School

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Lake Shared Campus

Project Updates

 Quality Learning Environments

Status: Scheduled for completion in 2019
Scope of Work:
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria)
  • Additional main office for shared campus
  • Additional science lab for shared campus

 Maintenance

Status: In progress
Scope of Work:
  • Add exit lighting – complete
  • Classroom level air conditioning solution
  • Emergency lighting for stage
  • Interior LED lighting upgrade
  • Repair/Upgrade Fire Sprinkler systems
  • Replace selected roofing
  • Safety upgrades in kitchen – complete
  • Improve existing cooling and ventilation systems

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

Construction Updates

2012 Bond

Bond Investment (Approximate):

$2,580,097

Key Project Elements:

Replace boilers; cooling enhancement; potable water distribution; ADA improvements; code upgrades; correct science safety issues; student technology.

STRIVE Prep – Lake Annual Mill Investment (Approximate):
230000

Lake International School Annual Mill Investment (Approximate):
420000