*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.
2015
*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.
Maintenance |
Status: CompleteScope of Work:
|
Technology and Safety |
Status: CompleteScope of Work:
|
$26,870,000
New ECE-8 building that consists of a gym, library, cafetorium and 26 classrooms, with an area for future expansion; bio-retention pond; student technology.