School-determined Budget

$150,000

Original Construction Date

1955

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Gust

Project Updates

 Quality Learning Environments

Status: Scheduled for completion in 2020
Scope of Work: 
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria).

 Maintenance

Status: In progress
Scope of Work:
  • Exterior LED lighting upgrade – complete
  • Interior LED lighting upgrade – complete
  • Masonry repairs
  • Repair/update fire alarm system – complete
  • Replace exterior door locks
  • Replace technology-related cooling systems
  • Improve existing cooling and ventilation systems – complete

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

Construction Updates

2012 Bond

Bond Investment (Approximate):

$846,353

Key Project Elements:

Code upgrades; replace A/C in telecommunications room; cooling enhancement; computer lab upgrades; student technology.