School-determined Budget

$1,620,000

Original Construction Date

1953

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Project Updates

 Quality Learning Environments

Status: Scheduled for completion in 2020
Scope of Work:
  • Funding to make school determined investments that may include: Classroom Upgrades, STEM/STEAM labs, Carpet/Tile/Paint/Furniture, Restrooms, Front Office, Gym/Auditorium/Cafeteria/Library, Lockers, Signage

 Maintenance

Status: In progress
Scope of Work: 
  • Install Fire Sprinklers
  • Repair concrete overhangs at exterior entrances
  • Resurface parking lot
  • Water service replacement – complete
  • Improve existing cooling and ventilation systems – complete

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

Construction Updates

2012 Bond

Bond Investment (Approximate):

$1,362,607

Key Project Elements:

Roofing; new boilers; cooling enhancement; fire alarm and detection systems; code upgrades; correct safety issues in science classrooms; ADA improvements; student technology.