School-determined Budget

$500,000

Original Construction Date

1925

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Project Updates

 Quality Learning Environments

Status: Scheduled for completion in 2019
Scope of Work:
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria).

 Maintenance

Status: In progress
Scope of Work:
  • Classroom level air conditioning solution
  • Interior LED lighting upgrade – complete
  • Repair/upgrade fire sprinkler systems
  • Repairs to electrical terminals
  • Replace boiler components
  • Safety upgrades in kitchen – complete
  • Improve existing cooling and ventilation systems
  • Replace playing field artificial turf – complete
  • Bond premium project: elevator maintenance

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

Construction Updates

2012 Bond

Bond Investment (Approximate):

$4,487,355

Key Project Elements:

Replaced boilers; replace A/C in telecommunications room; cooling enhancements; science room fume hoods; ADA improvements; code upgrades; renovation of science classrooms; art kiln; renovate Butler buildings; operable partition at computer lab; student technology.