School-determined Budget

$130,000

Original Construction Date

1951

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Project Updates

 Quality Learning Environments

Status: Scheduled for completion in 2020
Scope of Work:
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria).

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

2012 Bond

Bond Investment (Approximate):

$4,070,000

Key Project Elements:

4-classroom addition; roofing; maintenance to address boiler issues; code upgrades; cooling enhancement; ADA improvements; replace A/C in telecommunications room; furniture; student technology.