School-determined Budget

$110,000

Original Construction Date

1953

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Project Updates

 Quality Learning Environments

Status: Complete – see details and photos here
Scope of Work:
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria).

 Maintenance

Status: Complete
Scope of Work:
  • Interior LED lighting upgrade
  • Improve existing cooling and ventilation systems

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

2012 Bond

Bond Investment (Approximate):

$272,590

Key Project Elements:

Outdoor Sustainability Project; replace A/C in telecommunications room; cooling enhancements; fire alarm and detection systems; code upgrades; ADA improvements; student technology.