School-determined Budget

$2,550,000

School Type

Shared Campus (Abraham Lincoln, Compass, Respect)

Original Construction Date

1960

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

Project Updates

 Quality Learning Environments

Status: Complete
Scope of Work:
  • Remodel to create additional classrooms 
  • Funding to make school determined investments

 Maintenance

Status: Complete 
Scope of Work:
  • Classroom level air conditioning solution
  • Interior LED lighting upgrade
  • Repair/Upgrade Fire Sprinkler systems
  • Replace galvanized piping
  • Various ADA improvements
  • Improve existing cooling and ventilation systems
  • Replace playing field artificial turf

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

2012 Bond

Bond Investment (Approximate):

$7,574,491

Key Project Elements:

Roofing; A/C in telecommunications room; cooling enhancement; potable water distribution; code upgrades; ADA improvements; library power upgrades; replaced freezer/cooler; student technology.