School-determined Budget

$80,000

Original Construction Date

1970

*Note: 2016 Bond Budget represents direct construction costs. Not inclusive of design and management services, insurance allocations and inflation.

School photo shoot at Cheltenham Elementary School in Sept. 2015

Project Updates

 Quality Learning Environments

Status: In progress 
Scope of Work:
  • Funding to make school determined, high-impact investments that may include areas such as classroom upgrades, furniture upgrades, or common space upgrades (front office, gymnasium, cafeteria).

 Maintenance

Status: Complete
Scope of Work: 
  • Interior LED lighting upgrade
  • Replace selected roofing
  • Improve existing cooling and ventilation systems

Technology and Safety

Status: Complete
Scope of Work:
  • Additional funding for student devices
  • Network and infrastructure
  • Safety investment in door hardware to support lockdown and upgrading existing systems

2012 Bond

Bond Investment (Approximate):

$4,580,000

Key Project Elements:

Classroom renovation to convert from open plan; roofing; maintenance to address boiler issues; replace A/C in telecommunications room; air distribution insulation; code upgrades; sanitary sewer pipes repair; furniture; student technology.