Rachel B. Noel Campus

5290 Kittredge St, Denver, CO 80239

Year Built: 2002


2012 Bond

2012 Bond Investment (Approximate): $1,338,037

2012 Key Project Elements:

Replace A/C in telecommunications room; theater and stage equipment; ADA improvements; interior signage; school/community garden; student technology.

KIPP Montbello College Prep Annual Mill Investment (Approximate): 280000

Collegiate Preparatory Academy Annual Mill Investment (Approximate): 450000


2016 Bond

Proposed 2016 Bond School-Determined Budget (Approximate): $80,000

Proposed 2016 Bond Key Projects:

Interior LED lighting upgrade; Replace Fire Alarm and Detection System; Funding to make school determined; high-impact investments that may include areas such as classroom upgrades; furniture upgrades; or common space upgrades (front office; gymnasium; cafeteria); Additional funding for student devices; Network and infrastructure