Merrill Campus

1551 S Monroe St, Denver, CO 80210

Year Built: 1953


2012 Bond

2012 Bond Investment (Approximate): $1,460,014

2012 Key Project Elements:

Remodel/renovation for a 7-classroom school on the lower level; concrete walk; replace A/C in telecommunications room; cooling enhancement; code upgrades; correct science safety issues; student technology.

Creativity Challenge Community (C3) Annual Mill Investment (Approximate): 80000

Merrill Middle School Annual Mill Investment (Approximate): 410000


2016 Bond

Proposed 2016 Bond School-Determined Budget (Approximate): $2,800,000

Proposed 2016 Bond Key Projects:

Improve existing cooling and ventilation systems; Replace Fire Alarm and Detection System; Resurface parking lot; Various ADA improvements; Funding to make school determined investments that may include: Classroom Upgrades; STEM/STEAM labs; Carpet/Tile/Paint/Furniture; Restrooms; Front Office; Gym/Auditorium/Cafeteria/Library; Lockers; Signage; Additional funding for student devices; Network and infrastructure