Godsman

2120 W Arkansas Ave, Denver, CO 80223

Year Built: 1958


2016 Bond

2016 Bond School-Determined Budget (Approximate): $110,000

2016 Key Project Elements:

Improve existing cooling and ventilation systems; Interior LED lighting upgrade; Replace boiler; Funding to make school determined; high-impact investments that may include areas such as classroom upgrades; furniture upgrades; or common space upgrades (front office; gymnasium; cafeteria); Additional funding for student devices; Network and infrastructure


2012 Bond

2012 Bond Investment (Approximate): $3,334,765

2012 Key Project Elements:

4-classroom addition; roofing; cooling enhancement; code upgrades; student technology.