DCIS at Ford

14500 Maxwell Pl, Denver, CO 80239

Year Built: 1973


2012 Bond

2012 Bond Investment (Approximate): $382,484

2012 Key Project Elements:

Replace A/C in telecommunications room; ADA improvements; code upgrades; replace mechanical ducts; student technology.


2016 Bond

Proposed 2016 Bond School-Determined Budget (Approximate): $90,000

Proposed 2016 Bond Key Projects:

Improve existing cooling and ventilation systems; Interior LED lighting upgrade; Replace boiler and storage tank; Replace boiler components; Funding to make school determined; high-impact investments that may include areas such as classroom upgrades; furniture upgrades; or common space upgrades (front office; gymnasium; cafeteria); Additional funding for student devices; Network and infrastructure