Castro

845 S Lowell Blvd, Denver, CO 80219

Year Built: 1993


2012 Bond

2012 Bond Investment (Approximate): $370,288

2012 Key Project Elements:

Replace A/C in telecommunications room; code upgrades; ADA improvements; student technology.


2016 Bond

Proposed 2016 Bond School-Determined Budget (Approximate): $100,000

Proposed 2016 Bond Key Projects:

Exterior LED lighting upgrade; Interior LED lighting upgrade; Safety upgrades in kitchen; Funding to make school determined; high-impact investments that may include areas such as classroom upgrades; furniture upgrades; or common space upgrades (front office; gymnasium; cafeteria); Additional funding for student devices; Network and infrastructure